art camp count down – minus 16

Today we continued with pipe installation for the toilets.

And we connected tubes.

We prepaired the wastewater pipes for the showers.

We added some plastic protection for the wood paletts.

We prepared the space for the two sinks.

And the basement for the toilets.

We prepaired the foundation for three water tanks in a higher level. This tanks will be used to store water for the art camp.

We moved one ibc tank to the new storage place and we charge it with water this night.

Half the way between the water storage and the shower area we placed the foundation for the solar water heater.